See lead time, value-add time and PCE for a chain of steps.
Takt = 58.7 s per unit — used to flag slow steps and to turn pieces waiting into time (wait = inventory × takt).
Waiting makes up 98.7% of lead time. Shortening waits usually beats speeding up the work.
Opens the editor with these steps, waits and takt as a ready-to-edit map. No account needed.
The time ladder lines up your steps from left to right. Raised plateaus are value-add time (P/T); the flat sections between them are waiting. It totals lead time, value-add time and process cycle efficiency (PCE = value-add time ÷ lead time).
Most of the time a product spends in a process is waiting, not being worked on, which is why PCE is usually small. A ladder with long flat sections tells you where the stock is piling up; shortening those waits is usually a faster win than speeding up the work itself.
VA time = sum of P/T Lead time = sum of C/T + sum of waits Wait = inventory × takt (Little's Law) PCE = VA time ÷ lead time × 100
Three steps with C/T 45, 70 and 50 s and P/T 40, 55 and 30 s, with 120 and 80 pieces waiting between them at a takt of 58.7 s: waits total 200 × 58.7 = 11,739 s, lead time = 165 + 11,739 ≈ 11,904 s (3.3 h), VA time = 125 s, so PCE ≈ 1.1%.
Single-digit PCE is common in value streams that have never been mapped, because waiting dominates. Treat it as a trend to improve, not a pass mark: the same map redrawn after a kaizen should show it rising.
P/T (process time) is the hands-on, value-adding time for one unit. C/T (cycle time) is how often a unit leaves the step, so it also includes time lost to waiting for parts, adjustments or handling.
Inventory × takt. If 120 pieces are queued and one is consumed every 58.7 seconds, the last one waits about two hours. You can also type the wait in directly.
PruneChart draws the whole value stream, flags every step slower than takt in red, and works out lead time and PCE as you build.